• Login

Articles by James A Robertson and Associates

Cnf 011 The Benefits of Management Information Systems to the Professional Practice -- V3 Consulting Engineers Case Study
Created by James on 8/19/2014 2:02:19 PM

Case study with regard to a fully integrated business information system (ERP) with Cubic Business Model in the financial suite which delivered exceptional benefits in terms of management information and management effectiveness as well as substantial efficiencies including head count reduction and drastically reduced audit time and cost


The Benefits of Management Information Systems to the Professional Practice

SAICE 15th Annual Conference on Computers in Civil Engineering

By

Dr James A Robertson PrEng & Reg M Barry, Financial Director, V3 Consulting Engineers


SYNOPSIS

The advent of commercially available practice management software for the South African Consulting Engineering Industry some years ago, introduced the possibility of introducing far reaching, tailored, management information systems into the professional practice. This paper sets out to highlight some of the experiences and particularly the benefits derived from one such installation two years after implementation. The system comprises an integrated job costing, billing, debtors and creditors system linked to a comprehensive financial management system and an executive information system offering a wide range of management reports and graphical analysis.

Benefits experienced include the reliability and timeousness of the information, financial results are typically available within ten days of month end and year end financials within the same time frame at reduced audit cost and greater precision. A wide variety of reports are available and the organization can be viewed as a "Rubics Cube" of information in which the information can be grouped and examined in a wide variety of ways allowing project, client, profit center and other views of performance according to management's needs. Full activity based financial analysis and overhead distribution is supported eliminating the approximations typically made in assessing profit distribution and recognizing marketing and management contributions.

Senior management have had their workloads on mundane analysis greatly reduced while obtaining more accurate information faster. Information is also available at different levels of the organization at different levels of detail. Enquiries from a very summarized executive view to a very detailed transaction level analysis allow effective management by exception with drill down to specific problems. The variety of analyses possible offers great scope for effective management and directed marketing in a manner which should allow the company to create and sustain competitive advantage.

 

INTRODUCTION

The evolution of computer technology in the late eighties gave rise to a situation at V3 Consulting Engineers in 1989 where the existing projects system was becoming obsolete and no longer able to cope with the demands of the firm. Over the period 1989/90, the management of the firm undertook a number of preliminary reviews of commercially available software and subsequently commissioned a detailed study of the firm's requirements in which the relative strengths and weaknesses of the commercially available software packages was evaluated (Robertson 1990).

It was established that neither of the major packages available were ideally suited to the needs of the firm and further analysis was undertaken to establish in greater detail the scope of modifications required. Following negotiations with the vendors, a scope and budget for the required changes was agreed and a final decision taken as to which system to purchase. The selected system was a South African developed package already in use at a number of consulting engineering firms.

A period of software enhancement by the developers was followed by testing and pilot operation, the system was commissioned and ran live in the Cape Region of V3 in October 1991. Thereafter the system was installed in the Free State and Transvaal regions, running live from March 1992.

This paper outlines some of the experiences with the implementation with particular emphasis on the benefits derived from the use of the system.


SYSTEM OVERVIEW

The system selected comprised a number of major components:

Projects System

The projects system comprises a suite of programs including projects and personnel databases, salary and rates information. A company parameters module allows configuration of the system to model the organizational structure of the practice to take account of offices, departments and associated companies as well as to define the nature of the general ledger interface. A variety of set-up options allow further customization of the operation of the software.

The projects system provides full features for the entry and processing of time and expense information with comprehensive analysis of Work in Progress (WIP). WIP is maintained on an open item basis such that once captured, all items remain in the system until they are either recovered through billing to the client or written off. Full audit trails and analysis reports are available on the WIP. The project system includes a largely automated billing system.

The projects system also provides a wide range of facilities for structuring up to 5 levels of project detail and associated analysis together with activity codes and a variety of project budgeting and reporting options.

The projects system is integrated with debtors and creditors modules to allow full management of these accounting functions with project related reporting in debtors and both project and non-project expenses posted in the creditors program.

All financial components of the projects system are integrated on a batch basis with a commercial general ledger package.

Financial System

The financial system comprises a commercial general ledger package together with integrated cash book software. This is linked on a batch basis to a commercial salary package. The financial system has recently been extended by the acquisition of an integrated assets register package and barcode reader. The financial system replaced 24 column manual cash books.

The general ledger chart of accounts accommodates a comprehensive, fundamental analysis of all income statement and balance sheet items in a manner that is linked to the business model of the organization in terms of cost and profit centres including physical branch offices and administrative, technical and support departments. A hierarchical, structured coding scheme is employed in order to facilitate allocation of expenses on an activity basis, and to allow progressively more detail in enquiries. Associated with the chart of accounts, a variety of financial reports allow summary or detail reporting for the region, office or department as required, including summary and detail income statements, balance sheet, cash flow projections and ratio analysis.

The financial system is linked directly to the projects system in a manner that is designed to support activity based costing and allocation of income and expenses in a manner that permits clear definition of ownership of information with a view to achieving a high level of internal auditing and a resultant improvement in accuracy and reduction in audit delays.

National Consolidation

In the past year, procedures have been implemented to permit all financial results to be consolidated nationally at the detail level, thus permitting the extraction of a wide variety of detailed and summary analyses. Various controls on inter-region charges have also been implemented together with procedures for accumulation and distribution of corporate overheads.

Executive Information System

Recently a graphical Executive Information System (EIS) has been developed to operate on the underlying operational projects and financial systems. This EIS has been developed using a commercial, windows based tool and provides a high level of graphical summarization of certain key values in the projects and financial systems. Development is continuing.

The EIS system has been developed with the objective of enabling senior management to see key values summarized graphically in a meaningful way that allows them to rapidly identify potential problems and drill down to the detail in any way that they may consider necessary. Particular emphasis was placed on achieving a user interface that was intuitive for senior management and did not restrict enquiries on the basis of simplifying assumptions made during construction. The EIS also provides an interactive mechanism for overhead distribution on an activity basis, whereby all income and expenditure relating to non-production business units is distributed over the production units on an agreed basis. The model has been designed with a view to providing management with the means to examine the effect of alternative allocation formulae on the profitability of individual business units without altering the underlying data which has been allocated on a fundamental basis.

The ultimate objective set for the EIS is to support a "paperless board meeting" in which all relevant information is projected onto a screen in the board room so that managers can analyze and query information interactively and pro-actively thus facilitating management by exception rather than tabling large volumes of information.


OBJECTIVES FOR THE SYSTEM

A number of short term and long term strategic objectives were set for the system at the time that the initial investigation (Robertson 1990) was undertaken. Particular emphasis was placed on specifying the objectives and requirements for the system with the objective of meeting the long term strategic requirements of the firm with a view to avoiding the need to replace the system after a few years. Objectives set included:

- Provide tools to monitor and improve productivity and profitability.

- Enable profitability to be measured on a project, department and office basis using the cubic model proposed by Robertson.

- Assist the firm to offer the highest possible levels of service to it's clients.

- Ensure that charges for work were realistic and that work was performed effectively for the client.

- Provide comprehensive budgeting facilities for projects and financials.

- Assist in the evaluation of current and future directors with respect to appointment and promotion.

- Provide concise management summaries.

- Permit a global view of the practice.

- Permit detailed enquiry on all aspects of operations and job costing.

- Require minimum management time and manpower to operate system.

- System must be affordable.

All of these objectives have been met at the current time although costs have been greater than expected and would be handled differently if the project was undertaken today. Certain specific benefits are discussed in more detail in subsequent sections.


IMPLEMENTATION EXPERIENCE

The implementation was undertaken in a phased manner, as outlined previously. Problems were experienced in terms of availability of senior personnel in-house at certain times and in terms of commissioning the system in other regions using in-house personnel. This was undertaken with a view to cost containment but ultimately gave rise to increased costs associated with correction of problems experienced.

With hindsight, more use should have made of outside assistance in the implementation in the second and third regions. In-house staff were not experienced enough and the time they spent in other regions placed pressure on their own region's operation.

Time taken to achieve understanding and commitment to the new system by managers and staff at all levels proved to be greater than anticipated and required focused and firm action by top executives before all required information was provided by project leaders and other staff and proper use was made of management reports. Experience tends to support the widely reported view that a paradigm change of this magnitude requires between three and five years to become permanent in an organization.


BENEFITS OF THE SYSTEM

The projects system has now been in operation in the Cape Region of V3 for close to two years and in the rest of the country for eighteen months while the financial system has been in use country wide for eighteen months. As stated above, the objectives set three years ago have all been met. Specific benefits are discussed in the sections that follow:

Reliability and Timeousness of Information

Information is readily available, in many cases almost instantly. For example, analysis of time sheet data and other data captured to projects is available within two working days of the end of the month.

Full analysis of project performance for the month is available immediately data capture is completed including a wide variety of budget, costing and profitability reports. Up to date sales journals are available at any stage as are debtors and creditors age analyses. The EIS projects analysis can be made available within twenty four hours of month end or updated more frequently as appropriate.

Full financial statements including summary and detailed income statements, balance sheets and cash flow projections are generally available ten days after month end and include all closing and balancing adjustments for the period in question so that there is considerable confidence in the reliability of the information. The EIS financial analysis can be made available at the same time.

Because of the wide variety of combinations and groupings in which the information can be presented and the wide variety of controls built into the system, it is possible for all information to be reported in a manner which allows recipients to accept full ownership of specific sets of data. This facilitates verification and control and allows senior management to operate on the basis that, "if all subordinate managers have accepted the accuracy of their figures, the consolidated figures must be correct". This ensures a high degree of reliability and confidence in the information.

As a result of the detailed analysis contained in the general ledger, it is possible to operate the financial system in such a way that very little additional processing is required at year end over that required at month end. While some difficulties were encountered at the end of the first year of operations since not all procedures were fully in place, it was still possible to table the year end figures 17 days after the end of the year and they were signed off without qualifications by the auditors approximately five weeks later.

The Cubic Business Model

The business model referred to earlier allows the databases to be viewed as a multi-dimensional "Rubic's" cube which can be rotated and viewed in a wide variety of different ways. This permits the financial and production information to be grouped and summarized by office, department and region. Production (project) information can also be viewed by project leader, technical director, marketing director, client market segment, project discipline and client thus providing a fully market focused information capability. This information can then be used to focus marketing efforts and identify different marketing and management styles required for different market sectors as well as enabling management to evaluate the performance of individuals in terms of marketing and management contribution as well as production contribution.

In conjunction with these facilities, the activity based allocation of administrative overhead contribution by technical staff permits an accurate measurement of true profitability of individual business units or sub-units at a level which permits "level playing field" comparisons of business units. This eliminates the traditional problem of professional service organizations where the business units of those involved in management and marketing are penalized since only the production contribution is measured. Through this approach, inappropriate management decisions resulting from incorrect cost allocation can be avoided.

The system also supports attribution (allocation) of income from professional fees to the business unit employing the person doing the work. This permits the profitability of business units to be measured in terms of true, salary linked, revenue contribution as well as by the traditional method of project profitability and reduces the dependence on relatively arbitrary, rates based, costing approaches.

Senior Management Work Load and Effectiveness

Senior management have had their work load on mundane analysis greatly reduced as many of the analyses previously performed using spreadsheets have been incorporated into the system and are therefore available automatically with greatly reduced effort. Time spent resolving problems of mis-allocation and addressing queries with regard to year end has also been considerably reduced.

The multiple levels of summarization in conjunction with the high level of detail of the underlying data enable management to receive very summarized reports for routine management while affording them the capability to rapidly "drill down" to progressively more detail in order to answer queries.

Strategic Advantage

The wide variety of analyses available and the ready availability of information have freed management to be more effective while devoting less time to management and administration. At the same time, management have greatly improved scope to identify opportunities to improve operational effectiveness, increase delegation and improve profitability. They are also able to identify market related factors that can have a bearing on marketing strategy, product mix and other matters. These factors all enable the firm to offer innovative and competitive services in a competitive market. This is expected to assist the firm in creating and sustaining competitive advantage over the medium- to long- term as part of it's commitment to providing relevant, appropriate and cost effective services.


CONCLUSION

The components of a management information system (MIS) and associated financial and executive information systems have been summarized based on the experience of V3 Consulting Engineers. Certain experiences during implementation have been summarized and the objectives set for the system at the outset are reviewed. It is noted that these objectives have been met.

The benefits experienced by the firm are discussed with particular reference to issues such as timeousness and reliability of information, flexibility of analysis and control. It is noted that the work loads of senior management have been reduced while more accurate and detailed information is made available more rapidly. The ability to summarize the information in a great variety of ways while providing the ability to undertake enquiries at a very high level of detail when required, is noted as a further benefit.

It is concluded that the system has met most of the objectives set for it at the outset and that it is assisting the firm in it's objective of creating and maintaining competitive advantage through the provision of focused, appropriate and cost effective consulting engineering services.


REFERENCES

Robertson J A (1990) Report on Investigation Into Professional Practice Management Information Systems for Vorster, van der Westhuizen and Partners Unpublished report, October 1990.

September 1994

Download the V3 Consulting Engineers: The Benefits of Management Information Systems to the Professional Practice -- Article in Adobe pdf format



011 The Benefits of Management Information Systems to the Professional Practice -- by Dr James A Robertson PrEng from James Robertson


Download The Benefits of Management Information Systems to the Professional Practice v 003 -- Slides in Adobe pdf format

Download The Benefits of Management Information Systems to the Professional Practice v 003 -- Original Paper in Adobe pdf format


print
[MAKERATING] The comment feature is locked by administrator.
Sort by:
Return


Random Selection of Articles by Dr James Robertson

Subscribe to our StratNews newsletter

Click here to send us an email subscribing to our free newsletter -- all articles posted by James Robertson will be emailed to you

Dr James A Robertson PrEng The ERP Doctor

Business Systems NOT delivering?

Call the Business Systems Specialist

Dr. James Robinson

Dr James A Robertson -- has been involved in the effective application of Business Information Systems, including but NOT limited to ERP, since 1987 and in the profitable and effective use of computers in Business since 1981.

Drawing on a diversity of experience, including formal military training in Quick Attack techniques at the Regimental Commander level, Dr Robertson has developed highly effective methods of investigating any sub-optimal Business Information Systems situation -- be it an established system or a stalled project or any other source of Executive frustration -- quickly and concisely diagnosing the root cause of the problem and prescribing concise practical actions that Business Executives can effectively act on see the Pulse Measurement page and also the Sample Reports page for redacted real reports.

He has also developed highly effective methods of strategically enriching systems to unlock the full potential of existing investments, see the Precision Configuration page and couples this to architecting small pieces of clever software that harness the full potential of your investment, see the Software page.

If you are having problems with your systems, your project or your IT Department, call The Business Systems Specialist
James@James-A-Robertson-and-Associates.com

Business System Failure is RIFE -- we offer insight into why this happens AND WHAT is required to prevent it.

Failure is at epidemic levels with massive damage done to client companies -- if you are NOT aware of the extent of the problem please visit the About Failure page for a catalog of major failures running to billions of Pounds and Dollars.

All evidence indicates that the established players do NOT know how to deliver stable, reliable high value solutions that WORK.

There HAS to be a better way!

This website provides information relating to that way with a large collection of white papers, presentations, standards documents, etc that you can use to start bringing the situation under control

We also offer high level advisory services with regard to the application of the principles advocated on this website

We offer an ENGINEERING APPROACH to addressing these issues

Click here to read more about the Engineering Approach

By Engineering I mean the formal, structured, highly disciplined, highly systematic, highly practical approach that consistently delivers results in ALL areas of human endeavor where formally trained and certified engineers are the ONLY practitioners permitted to operate -- think large buildings, factories, motor vehicles, aircraft -- highly complex systems that work at a level that we take it for granted that they WILL work and where failure is all but unthinkable and, when it happens, attracts immediate public attention and rigorous investigation directed at ensuring that such failures are prevented in the future -- in fact, everything that the management consulting industry that implements complex software systems is NOT

This approach is discussed further on the Engineering Approach page.

Book -- The Critical Factors for Information Technology Investment Success

In 2003 I undertook an in-depth analysis of all the information and experience that I had gathered with regard to the factors giving rise to Business Information System failure including ERP and general IT and classified this information into a number of categories including "The Factors Causing Failure" and "The Critical Factors for Success" based on this I developed a two day Course "The Critical Factors for Information Technology Investment Success" which is still offered today.

Based on this I wrote the book of the same name, which is available in electronic form here for download:

Connect with James Robertson on LinkedIn

James has a very detailed profile on LinkedIn should you require further information about him.

You can also connect with him on LinkedIn at http://www.linkedin.com/in/DrJamesARobertsonERPDoctor

James has an open networking profile -- click on "Connect" and use email address James@LinkedIn-at-JARA.com.

Contact Us

You can contact us on

Email: James@James-A-Robertson-and-Associates.com

LinkedIn at http://www.linkedin.com/in/drjamesarobertsonerpdoctor

Facebook at https://www.facebook.com/james.a.robertson.393

Mobile: +44 (0) 776-862-2875

Landline: +44 (0) 207-059-0007

Fax: +44 (0) 844 774 4580

Articles by James A Robertson and Associates

There is a large body of white papers, articles and other content produced by Dr James Robertson available on this website

Please click here to visit the detailed listing of articles


Random Selection of Articles by Dr James Robertson

Std 026 Old Software IS Viable

Many business information system projects are motivated on the basis that the existing systems are obsolete.  This article challenges that argument with regard to a significant number of systems and presents information that will enable executives and managers to take a pragmatic view of this debate
Cnf 060 Why Information Technology In Managed Healthcare Does Not Deliver What Is Expected And How To Fix It -- Slides

Healthcare industry standard codes like ICD 10 and CPT 4 are amongst the worst examples of bad computer data engineering practice in the world today, there is huge scope for improvement in ways that will allow the application of computer based maintenance management techniques to be applied in countries where there is a severe shortage of qualified medical practitioners, the case for investing in such code schemes is present
SNw 057 Business System Failure – HOW do you recognize it?

Many executives and managers do NOT know how to recognize business systems failure.  They have failed systems right at their finger tips, gauged by the standards advocated on this website, BUT they do NOT realize that they are at some level failures and, because they do NOT recognize failure they do NOT recognize either the need OR the opportunity to DO something about it
Prd 043 Strategic Guidance and Advisory Services

Overview of the full range of services that are offered by James A Robertson and Associates
Sem 05 IBIS – The Strategic View of Business Information

A three hour Executive Briefing that outlines the most important aspects of what I advocate with regard to Integrated Business Information Systems, including ERP
SNw 042 The Real Issues in BIS: Introduction

This article provides an overview of the main components of the approach to Business Information System investment success as first detailed in my book in 2004 and elaborated on and taught since then

ArticleTagCloud for Articles Published by James A Robertson and Associates

7 steps to FIX your ERP      80:20 regarding software replacement      aborted projects      abstract      abstractness      accounting      actionable      adjudication      Advantage Data Transformer      advisory      agreement      all possible classifications      all reports      all software elements required      all spreadsheets      all tasks required to execute the project      Alpha Omega      analysis of data      analytics      animation      answers to the questions we have NOT yet thought to ask      Armscor      arrogant ignorance      art of strategic business information system project leadership      ASCO      attendance register      attorney      audit      audit cost reduction      bankrupt organizations      basis for achieving alignment      basis of payment      basis of pricing      better way      bid adjudication      bid adjudication score sheet      bid compliance      bid compliance checklist      bill of materials      bill of services      BIS      BIS failure      BIS success      boots in the mud      BPM      BPM dangerous      BPM distracting      BPM ineffective      brainstorming      break it until it does NOT break anymore      break it until it will NOT break any more      budget      budgeting      business engagement      business executives      business improvement      business information system      business information system failure      business information system success      business information system taxonomies      business information systems      business information systems procurement      business information systems projects      business integration      business intelligence      business intelligence models      business knowledge and experience      business participation      business process      business process mapping      business requirements focused      business requirements specification      business simulation laboratory      business systems      business systems laboratory      business understanding      by the book      care      case studies      case study      CEO      CEO -- project leader communication      CEO as custodian      CEO definite views      certificates      challenges      challenging presentations      change facilitation      change for strategic reasons      chart of accounts      classification schemes      clever software      client changing scope      client compact      clinical codes      coaching      Cobol      COBOL CAN be retained      Cobol still viable      code schemes      coding conventions and standards      cognitive span      collapse      communication      competitive advantage      competitive advantage through precision configuration      competitiveness      compiler      complexity      compliance      compliance checklist      comprehensive testing      Compuware      conference speaking      conferences      confidentiality      configuration      consultant NOT delivering what required      contract      contract certificates      contract law      contracting      contractors      corporate planning      cost      cost-quality-time      CPT 4      CPT4      critical factors      critical factors for IT investment success      critical factors for success      critical factors for technology success      critical human foundation      critical issues      critical issues analysis      critical requirements      CRM Risk Control      cubic business model      custom development      custom software      customer focused      data      data content      data engineering      data entities      data warehouse      DB2      definitions      design against failure      design and development      design for success      determination of strategic essence      determining strategy      diagnostic code      diamonds in the dust      differentiated      differentiation      diffusion of innovations      discovery      dislike of failure      dispute resolution      do NOT change systems because of alleged software redundancy      do things competitors could NOT do      document pack      Dr James A Robertson      Dr James A Robertson PrEng      dramatic benefits      dramatically improved strategic management information      driver of success      Dunning-Kruger effect      ease of use      economic collapse      economics      effective communication      effectiveness      efficiencies      efficiency      efficient filing of emails      eliminate light bidders      email      engineer against failure      engineered data      engineering      engineering approach      engineering approach to strategy      engineering failure      engineering laboratory      engineering services      engineering solution design      engineering techniques      enhance differentiators      enhance the differentiators      enhancing the value of your present investment      ensuring project success      enterprise resource planning      ERP      ERP configuration      ERP failure      ERP procurement      ERP success      ERP taxonomies      ERP value      essence IS different      essence of business      essence of the business and how it thrives      ethics      examples      exceptionally bad code design      executive briefing      executive briefings      executive custody      executive decision support      executive engagement      executive forum      executive frustration      expose hidden agendas      facilitation      factors causing failure      factors causing IT investment failure      factors causing technology failure      factors to manage for success      failure      failure to address soft issues      fashion      file table of contents      Financial Information System      financial information systems      financial management      fixing your ERP      focus for projects      folder design      foundation for delivery      full training      functional entities      future      Gantt Chart      gap analysis      general ledger      George Paton      go-live      go-live certificate      governance      governance = care      governance failure      group consolidation      Group Consolidation Chart of Accounts      growth      gut feel factors      hand holding      harshest judge of governance      hate failure      head count reduction      health management software      hierarchies      high level requirements      high road      high value      high value implementations      high value solutions      high value systems implementation      highly effective chart of accounts      holistic view of solution      how do you achieve executive custody      how the organization differentiates itself      how to      how to do it      huge opportunity      human foundation      hype      Hyperion      IBIS      ICD 10      ICD10      importance of executive custody      improved management information      in-box rules      incremental enhancement of existing systems      ineffectiveness      inefficiency      information required from third party suppliers      information technology      information technology failure      Information Technology Strategy      information technology success      Informix      in-house courses      innovative software solutions      innovator      inside head of CEO      insightful      instructions      intangible      integrated business information system      integrated view of business      integrity      intelligent data      interactive training material      interview      invitation to bid      isolated CEO = explosion      IT      IT and strategy      IT Audit      IT failure      IT governance      IT lies      IT management      IT mythology      IT non-performance      IT people who lie      IT personnel socialization      IT procurement      IT projects that fail      IT strategy      IT systems      IT systems procurement      IT the harshest judge of governance      James Robertson      Jof Nelson      key performance indicators      Kirsten Speer      knowledge management      laboratory      lack of an engineering approach      lack of precision configuration      lack of strategic alignment      lawyer      leadership      legal agreement      legislation      lies      list of required software      listen carefully      litigation      logical entities      loss information      low road      loyalty      MacDonald      maintain code schemes      maintenance      maintenance management      Malcolm McDonald      management      management information      managing contractors      manual      marketing hype      master data      master data classifications      master test data      mature facilitation      mature facilitator      measurable      measures of alignment      mentoring      Microsoft Outlook      misrepresentation      missing link      mistique      morals      Munich      mystique      mythology      new future state      New South Africa      no drill down      non-disclosure      NOT classic project management      obsolete is a fashion statement      obsolete software      old software IS viable      once software works it always works      on-line seminars      opportunities      opportunity to turn the economy around      organizing Microsoft Outlook      orientation of IT staff      own business experience      passion to enable clients to thrive      people are part of the system      personality matrix      planning      platform for a tough contract      precisio      precision      precision configuration      precision configuration advisory      precision configuration leadership      precision data      precision taxonomies      Predictive Index      preparatory steps      prescribed table of contents      presentation technique      presentations      preventing failure      preventing falure      preventing project failure      pricing      principles      problem statement      procedure code      process      processor ignorant of language      procurement      procurement timeline      professional speaker      Professional Speakers Association of Southern Africa      profitability      programming languages are for the programmer      project facilitation      project leader      project leader -- CEO communication      project leadership      project management      project management IT project management      projects      prove it works      PSASA      psychology      psychometrics      public conferences      public presentations      public speaking      Pulse Measurement      quality      REAL issues in Business Information Systems      REAL value      recognizing failure      redaction      reduced audit costs      reduced head count      reference documents      Reg Barry      regulatory body      relationship Almighty      relationship orientated      remediation of existing systems      Rennies Group      reports      reports not reliable      request for proposal      requirements specification      results orientated      RFP      right things      rigorous process      rigorous strategic planning      risk management      Robert Priebatsch      robust business information systems procurement      robust business systems procurement      robust contracts      robust procurement      robust solutions      SAICE      SAP ABAP is similar to COBOL      scheduling procurement      scientific professional      score sheet      screen design      seminars      SEPT      service orientated      Service Orientated Architecture      simple techniques to enhance business information systems value      simulation      sloppy configuration      SOA      socialization      software      software assets      software design      software does NOT wear out      software is instructions for the bricklayer      software schedule      software specification      software specification standards      solution experience      solution knowledge      South Africa      South African Institution of Civil Engineering      speaking      Spirit Led      standards      strategic      strategic advisory      strategic alignment      strategic analysis      strategic analysis and design      strategic business improvement      strategic custom development      strategic definition      strategic discovery      strategic driver      strategic driving force      strategic engineered precision configuration      strategic engineered precision taxonomies      strategic essence      strategic financial information      strategic gap analysis      strategic governance      strategic information      strategic management      strategic management information      strategic plan      strategic planning      strategic project leader      strategic snapshots      strategic software      strategic solution architect advisory      strategic solution architect leadership      strategic solution architecture      strategically designed chart of accounts      strategy      strategy defined      strategy focused planning      Strategy Snapshot Toolset      StratGap      StratSnap      strengthen differentiators      structured analysis      structured chart of accounts      substantial management information      succeed by engineering against failure      success      successful deployment      survive      system knowledge and experience      table of contents      tailored presentations      take notes      taxonomies      taxonomy      taxonomy software      technology      technology failure      technology issues      technology management      tender document pack      tender pack      tender pack table of contents      test data      testing      The Critical Factors for Information Technology Investment Success      the Critical Factors for Success      the essence of the business      the essence of the business and how it thrives      the essence of the organization and how it thrives      the factors causing failure      the first hour      The REAL Issues in Business Information System success      things right      third party suppliers      third world countries      thrive      time      tipping point      tough certificates      tough contract management      tough contracts      tough procurement      tough terms      training      training material      treatment code      understanding of data      understanding the engineering approach      Uniface      unlocking value      use different languages for new components      V3 Consulting Engineers      validation data      value      versus process      video      webinar      webinars      weighted factors      what is executive custody      what is strategy      what is the essence of this organization and how does it thrive      what to do      where is IT going      why executive custody is required      why the organization exists and how it thrives      why your business information system is NOT delivering and HOW to FIX it      why your ERP is NOT delivering and how to fix it      workflow      writer     

Search Articles

Table of Contents

Home

About Dr James A Robertson PrEng -- The Business Systems Doctor -- and Other Topics

Catalogue of Major Business Information System Failures

About the Engineering Approach

James Robertson's Value Add

Attributes of a HIGH VALUE solution

Recognizing Business System Failure

The Critical Human Foundation

Old Software IS Viable

From South Africa

Competencies of Dr James A Robertson PrEng

About Professor Malcolm McDonald

Table of Contents

About my relationship with the Almighty Creator, Yah the Eternally Self-Existing

Comments relating to the Business Systems Industry and other topics

Testimonials and other positive material regarding James Robertson

Reference Articles

List of Articles

Article Catalogue

Achieving High Value Business Information System outcomes

Executive Custody -- What is it and HOW do you get it?

The REAL Issues in Integrated Business Information System Success

Part 1: Introduction

Part 2 -- Mythology and Lack of Executive Custody

Part 3 – Strategic Alignment and Precision Configuration

Why your ERP is NOT delivering and HOW to FIX it

IT Project Management

Pulse Measurement

CEO Anthony Lee Comments on his experience of the Pulse Measurement

No Charge Guarantee on the Pulse Measurement Service

Examples of Pulse Measurement Outcomes

Critical questions regarding the Pulse Measurement™

The Pulse Measurement Workflow

The Critical Factors for Business System (ERP+) Investment Success in the Pulse Measurement

Indicative Pulse Measurement Durations

What is a JAR&A Pulse Measurement?

Survival of the fittest – why it makes sense to measure the pulse of your business

Examples of Pulse Measurement Outcomes over 24 years

Sample Pulse Measurement Reports

Strategy

Strategic Essence: The Missing Link in Business Information Systems

Strategic Essence: Overview

Strategic Essence: Part 1 -- Strategy Defined

Strategic Essence: Part 2 -- Differentiation

Strategic Essence: Part 3 -- The Essence IS Different

Strategic Essence: Part 4 -- The Essence should be the Point of Departure

Strategic Essence: Part 5 -- Discovering Strategic Essence

Strategy -- the Essence of the Business: What is it and how do you develop actionable strategic plans?

Simple Steps to Increase the Strategic Value of your ERP Investment

Free Strategic Snapshot Toolset and Manual

A strategy focused planning system beyond traditional budgeting

Tough IT and ERP Procurement and Contracting that Works

Robust Business Systems Procurement

Part 1 -- Introduction

Part 2 -- Bill of Services, Laboratory, Go-live Certificate, etc

Part 3 -- Executive Engagement, Bid Compliance, Adjudication and other matters

Procurement Documents

Guidance and Advisory Services

The Art of Project Leadership

Why Regular Communication with the CEO is Vital

The Business Simulation Laboratory

Precision Configuration and Strategic Business Information Architecture

Precision Configuration based on Strategic Engineered Precision Taxonomies

The JAR&A Cubic Business Model

Highly Structured Strategic Chart of Accounts -- a Vital Element of your Corporate Information Arsenal

The Product Catalogue -- an Essential Element of any Precision Configuration

Attributes -- answers to the questions you have NOT yet thought to ask

Case Studies of Notably Successful Projects with high value Precision Configuration

092 Doing things differently and better -- ASCO Case Study 2-- BPM Summit 2013

088 Strategic ERP Invesment -- ASCO Case Study -- Service Management Conference and Exhibition Africa

026 Information Architecture and Design of FIS for Rennies Group -- Financial Information Systems Conf

018 CRM Risk Control: Designing and Implementing an Integrated Risk Mgmt Sys -- Integrated Risk Mgmt Conf

011 V3 Consulting Eng: Benefits of MIS to Professional Practice -- SAICE 15th Ann Conf on Computers in Civil Eng

Strategically Enriching your Business Information Systems

Part 1 -- Introduction

Part 2 -- Principles of Data Engineering

Part 3 -- Steps in applying these recommendations

Simple Steps to increase the strategic information value yield from your Business Systems Investment

The Full JAR&A Taxonomy Manual

Part 1: Introduction, Problem Statement, Definitions and Examples

Part 2: Why Use JAR&A, Required Knowledge and Experience, Cubic Business Model and Chart of Accounts and Taxonomy Software

Part 3: How to do it, Case Studies and White Papers and other References

Example General Ledger Manual

Business Process -- Irrelevant, Distracting and Dangerous

The RIGHT Approach

Custom Strategic Software Design and Oversight of Construction

Standards for Custom Software Specification

What IS Software?

IT Effectiveness

Organizing Outlook

Critical Factors for I.T. Success

A Moral and Ethical Dilemma -- Systems that Fail

Case Studies examining Business Information System failures

The BBC Digital Media Initiative Debacle

The Bridgestone -- IBM Conflict

Speaking and Training

Showcase of Conference Presentations

Most Viewed Presentations

Briefings and Seminars

Why your ERP/BIS is NOT delivering and HOW to FIX it

ERP and IT Procurement that Delivers Results

The Critical Factors for IT and ERP Investment Success

Other Seminars

Conferences and Public Presentations

Conferences 80 to 99 -- 2009 to Present

Conferences 60 to 79 -- 2005 to 2009

Conferences 40 to 59 -- 1996 to 2005

Conferences 20 to 39 -- 1994 to 1996

Conferences 01 to 19 -- 1989 to 1994

On-Line Seminars (Webinars)

Webinar on Preparing and Presenting Webinars

Contacting James A Robertson and Associates Limited