• Login

03 Wholesale Chemical Distribution Company – JD Edwards and Big Brand Implementer

Eighteen month JD Edwards implementation by big brand Consulting firm.  After five months of live operation warehouse output was still extremely slow and delivery promise was being consistently broken to just-in-time manufacturing clients.  The client was starting to lose their biggest customers.

Within five days established that the configuration was fundamentally flawed and that none of the consultants could explain why it was the way it was or what was required to rectify the problem.

Advised the CEO to return to previous system for business survival reasons and initiated discussion with previous service provider.  Client returned to previous system in five weeks and six months later referred to the decision as “the best decision we ever took”.

Report

REVIEW OF BUSINESS SYSTEMS
STATUS AT CLIENTCOMPANY03

A limited scope investigation was undertaken into the status of Business Information Systems at ClientCompany03.

Following are the findings of the investigation:

1. ALLEGATION OF NEGLIGENCE - POTENTIAL CLAIM FOR DAMAGES
There appears to be a basis to allege negligence against BigBrandImplementer03 with a view to claiming damages in terms of unbudgeted costs and loss of profits resulting from business disruption.

2. BUDGET CONSTRAINTS, POLICIES, APPROACH, IMPLEMENTATION
It appears that the budget was tighter than would have permitted a viable outcome and that there were other decisions and actions on behalf of ClientCompany03 which exacerbated the situation.  Includes decision to implement JDE "the same as ERP03".

3. SOURCE CODE FOR COMPACT
It is likely that ClientCompany03 can gain access to the ERP03 source code, either in terms of a letter that apparently exists or, if necessary, by legal action.  The originator of ERP03 is available to provide support for at least two years and possibly for five years.  This could potentially be extended.

4. WAREHOUSE -- CAUSE FOR CONCERN
The current state of the implementation of J D Edwards in the ClientCompany03 Inland Warehouse appears to be cause for significant concern.  It seems that there may be basic configuration issues as well as implementation issues that may require a substantial effort and investment to resolve.  This component is CENTRAL to the situation given the strategic driver of excellence in customer service which is largely attained through very short response times between time of order and time of delivery.

5. HIGH COST OF COMPLETION OF JDE IMPLEMENTATION
It appears that the additional cost to complete the implementation of JDE countrywide will amount to between £100,000 and £500,000 by end 2004.  This assumes an implementation which is consciously and actively designed to minimize further business disruption.

6. COST OF REVERTING TO ERP03 AND ENHANCING
It seems likely that ClientCompany03 could revert Inland to ERP03 and undertake modifications to improve overall efficiency for a cost of between £50,000 and £150,000 by end 2004.  Planning, data conversion, change management, etc for a minimum impact change back must not be under estimated.

7. OTHER - UPGRADE IN-HOUSE CAPABILITY
Need for a more comprehensive in-house capability - undertake an H.R. investigation.  Larger operating budget for I.T.


FURTHER INFORMATION
More details regarding the above factors is contained in Appendix 2.


RECOMMENDATION
The relative merits of ClientCompany03 completing the implementation of JDE countrywide versus reverting the Inland Division to ERP03 have been evaluated as set out in Appendix 1.  Based on this evaluation it is concluded that ClientCompany03 should revert the Inland Division to ERP03 and that JDE should be abandoned.  This is determined on the basis of weighted scoring in terms of critical factors for adjudicating the decision.

The move back to ERP03 in Inland should take place within a carefully managed project plan which addresses all necessary measures to minimize business disruption.  This may cost as much as £50,000.


NEXT STEPS
Following a decision to revert to ERP03 the following steps are recommended:

a. Negotiate a two year or five year support contract with regard to ERP03 with a longer term horizon of ten years if possible.

b. Establish a multi-disciplinary team to plan the return to ERP03 in Inland with minimum business disruption.

c. Contract a resource with excellent knowledge of ERP03 full time from Supplier03 for the duration of the project (2 to 4 months?).

d. Systematically plan and execute the necessary measures to move back to ERP03 at best possible speed within constraints of risk containment in terms of business impact.

e. Contract other resources.  Including secondment of staff from other divisions if necessary to relieve pressure and ensure project is well resourced.

f. Carefully designed and implemented communication program with staff and customers.

Yours faithfully


Dr JAMES ROBERTSON PrEng
JAMES A ROBERTSON AND ASSOCIATES
Achieving effective, sustainable competitive advantage and profitable, decisive corporate operation through effective application of I.T. and Strategy


APPENDIX A
EVALUATION OF RELATIVE MERITS
ERP03  AND J D EDWARDS



The relative merits off ClientCompany03 continuing the implementation of J D Edwards (JDE) or reverting to ERP03 were evaluated against the following criteria (relative importance in brackets as weight out of 100%):

1. SATISFY STRATEGIC DRIVER - CYCLE TIME (40%)
How well does each solution satisfy the strategic driver of excellence in customer service through consistently low order - delivery cycle times within the context of a low margin business?  
Rating -- Current: ERP03 = 8/10; JDE = 3/10: Forecast: ERP03 9/10; JDE = 7/10

ERP03 has been developed using ClientCompany03 as a benchmark.  JDE remains a generic package no matter how finely it is tuned.

2. LOW ESTABLISHMENT AND OPERATING COST (12%)
How well does each solution offer low overall establishment and operating costs within the context of a low margin business?
Rating -- Current: ERP03 = 9/10; JDE = 2/10: Forecast: ERP03 8/10; JDE = 5/10

ERP03 is in full operation in much of ClientCompany03 and is well known in Inland.  JDE has US$ denominated costs and corporate professional service fees whereas ERP03 has Rand denominated costs and small entrepreneur professional service fees.

3. RELIABILITY (20%)
How reliable is each solution in terms of expected up time, support, etc?
Rating -- Current: ERP03 = 9/10; JDE = 5/10: Forecast: ERP03 9/10; JDE = 7/10

JDE software is dependent on long distance support for bug fixes which can occur as evidenced by the debtors patch problem experienced after starting operation.  ERP03 is well established in ClientCompany03.

4. WORLD CLASS SOFTWARE (2%)
Is the software solution world class, is it acknowledged as such?
Rating -- Current: ERP03 = 3/10; JDE = 9/10: Forecast: ERP03 3/10; JDE = 9/10

JDE certainly meets all generally accepted criteria to be regarded as world class.  However, it is considered that goodness of fit to the ClientCompany03 business is more important.

5. WINDOWS SOFTWARE (1%)
Is the software Windows based?
Rating -- Current: ERP03 = 0/10; JDE = 10/10: Forecast: ERP03 0/10; JDE = 10/10

JDE is fully Windows based even to the point of apparently not supporting mouse free operation - this is regarded by the writer as a weakness.

6. QUALITY OF DATABASE, OPERATING SYSTEM AND HARDWARE PLATFORM (5%)
Is the technology platform on which the software solution resides of high quality?
Rating -- Current: ERP03 = 9/10; JDE = 9/10: Forecast: ERP03 9/10; JDE = 9/10

Both systems run on effectively the same platform.  The technology investment made for JDE can be used for ERP03 and will result in very significantly improved operating performance for ERP03.

7. EASE OF USE AND IMPLEMENTATION (20%)
How easy is the software for existing ClientCompany03 users to use; includes ease of implementation in remaining regions.
Rating -- Current: ERP03 = 9/10; JDE = 1/10: Forecast: ERP03 9/10; JDE = 7/10

It is likely that even with considerable tuning for ClientCompany03 JDE will still be more complex for new users to learn.


WEIGHTED SCORE RESULTS
Current: ERP03 = 9.8; JDE = 3.7; Forecast: ERP03 = 10.3; JDE = 7.5.  ERP03 rates 265% stronger than JDE on Current and 137% Stronger on Forecast.

In considering these ratings it is important to note that ERP03 has been in use at ClientCompany03 for approximately 15 years and that much of ERP03 was developed in close consultation with ClientCompany03.  ERP03 is therefore an excellent fit.


CONCLUSION
While JDE can certainly be made to work effectively and efficiently within ClientCompany03 the writer is unable to build a case for the rest of ClientCompany03 to change to JDE taking account of cost and business disruption and accordingly recommends that ClientCompany03 Inland reverts to ERP03.


APPENDIX B
FURTHER REMARKS ON FINDINGS



1. ALLEGATION OF NEGLIGENCE - POTENTIAL CLAIM FOR DAMAGES
This finding should be considered in the context of the actions by BigBrandImplementer03 (BBI03) in purchasing ERP03, discontinuing the product and effectively forcing ClientCompany03 to change their software.

It is the writer's opinion that the courts would have found against BBI03 had ClientCompany03 taken measures to oppose this action by BBI03.

The nett effect is that ClientCompany03 were pressurized into changing to JDE and then received professional support which it seems reasonable to regard as incompetent and / or negligent at a level that would warrant ClientCompany03 claiming substantial damages.

2. BUDGET CONSTRAINTS, POLICIES, APPROACH, IMPLEMENTATION
No further comment considered necessary.

3. SOURCE CODE FOR COMPACT
BBI03 have apparently acknowledged that ClientCompany03 are entitled to the source code for ERP03.

Supplier03, the originator of ERP03, has indicated that he is available to support ERP03 for two years and that subject to commercially acceptable terms with ClientCompany03 and other users he would entertain support for five years.

It is the writers opinion that if ClientCompany03 invest a portion of the total estimated cost to convert to JDE in a long term contractual relationship with Supplier03 and his associates it should be possible to secure a longer term of support.

In principle, provided a few other major users choose to remain with ERP03 long term there is no reason to expect that support will ever be terminated.

4. WAREHOUSE -- CAUSE FOR CONCERN
If ClientCompany03 are to remain with JDE then any action to optimize the operation of JDE should only take place after a comprehensive evaluation of exactly what the issues are.  This should be accompanied by a laboratory evaluation of possible courses of action to ensure that whatever  changes are made do, in fact, produce an overall reduction in cycle time in conjunction with high levels of stability, reliability, etc.

In the event of ClientCompany03 choosing to revert Inland to ERP03 the above recommendation also applies to JDE for the short term until ClientCompany03 Inland is ready to move back to ERP03.

This aspect of business operations is so critical and so sensitive that all actions with respect to JDE in this area should be meticulously analyzed and tested before implementation.

5. HIGH COST OF COMPLETION OF JDE IMPLEMENTATION
This cost estimate is based on a course of action directed at ensuring that the implementation of JDE in all regions is as smooth as possible and is accompanied by the absolute minimum business disruption.  It is strongly recommended that whatever expenditure is necessary to ensure efficient and effective implementation of JDE in each division is properly planned and budgeted.  This implementation should take account of any operational differences that may exist in different divisions.

The amount of time and manpower, and therefore cost, that is required to achieve minimum business disruption and maximum business effectiveness during and after implementation is considerably greater than the cost required to simply achieve implementation without taking account of business disruption.

6. COST OF REVERTING TO ERP03 AND ENHANCING
While the cost of reverting could be minimized and a case presented for this being a relatively painless exercise it is the writer's opinion that this is not a viable option.  ClientCompany03 Inland has experienced severe business disruption and all future changes should take place within a framework where the risk of further disruption of the business is consciously and actively minimized.

7. OTHER - UPGRADE IN-HOUSE CAPABILITY
It must be recognized that bringing in additional manpower without activities to keep them productively occupied will be counter productive.  A suitable mix of permanent staff and part time contracted personnel should be assembled in order to provide ClientCompany03 with a robust, sustainable, reliable in-house capability.

This should take place within the context of proposals to HoldingCompany03 in terms of overall management of Business Information Systems.



Random Selection of Articles by Dr James Robertson

Cnf 085 Precision configuration -- Information Technologies' orphan child

The single biggest "hard" factor in the under performance of business information systems relates to what I call "sloppy configuration", this presentation outlines a concept that I call "precision configuration" and explains how it can make a huge difference to business information system value delivery
Cnf 061 Analysing The Two Most Critical Factors for I. T. Investment Success: Executive Custody and Strategic Solution Architecture

Executive Custody of large integrated business information system projects is one of the critical weaknesses, this presentation discusses some of the key considerations with regard to this and also discusses the importance of strategic alignment and strategic solution architecture in achieving high value solutions
Web 03 Strategy -- What is it and HOW do you develop actionable plans?

A detailed discussion of strategy, determining strategy and presentation of a method that enables organizations to develop a comprehensive measurable and actionable strategic plan with resource estimates and key performance indicators in a structured and systematic method that also provides measures of alignment or lack of alignment and provides a basis to facilitate alignment

Sample Pulse Measurement Report for Fleet Management Client -- ClientCompany28 -- Health of Microsoft AX Project and Implementer28 Professional Services

 
Project had been running for three years and cost millions with NO deliverable with seriously toxic relationships throughout the Project Team

Clear evidence of implementer incompetence and possibly dishonesty, range of key measures prescribed to turn the situation around

Implementer was the IT consulting arm of one of the "Big 4" accounting firms

 

 Report

A Pulse Measurement investigation into the health of the Microsoft AX Project and associated services from Implementer28 was undertaken for ClientCompany28 from 14 to 19 March 2012.

 

This report summarizes headline level findings and recommended actions.

 

All recommendations should be regarded as provisional and might be refined in the event of further information coming to light but are regarded as a reliable headline level result.

 

Findings

Following are the headline findings, percentages at the end of headings give an indication of the relative importance of each point in making my recommendations.

 

1.       Toxic project psychology and low visibility of deliverables – 7%
The level of conflicting opinions encountered during this Pulse Measurement was in the upper 10% of what I have encountered in doing dozens of Pulse Measurements

There is a lot of finger pointing, Implementer28 are blaming ClientCompany28, ClientCompany28 are blaming Implementer28, Implementer28’s people are blaming their management, ClientCompany28’s people are blaming their management.  There are people who were only prepared to express opinions subject to explicit assurance of confidentiality.

A significant number of reports of people in tears, people swearing and shouting, planning to resign or resigned, etc

The psychology of the project in many areas is very toxic although there were some suggestions that there were improvements as a result of recent developments

Very difficult to get real clarity with regard to what was going on, had to dig for sight of deliverables, reports of work trashed and redone repeatedly, etc

Ratings of likelihood of a successful outcome ranging from 0 (trash immediately) to 6 or 7, several people thought the project should be aborted

I have given this point a relatively low rating because it is my opinion that while these are real issues they are the symptoms of the issues addressed below

2.       Lack of a clear strategic project definition – 22%
The thing that stands out about this project is the complete lack of a clear definition of the project goals, divergent opinions as to the essence of the business and the project, etc

There is no visible document that clearly and concisely sets out the goals of the project, the Essence of ClientCompany28’s business, what the final deliverable will be and how to get there

The bottom line is that the project is rudderless and drifting with no coherent view of what is being achieved and how it is to be achieved

It appears that Implementer28 do not see such a definition as important and have never made any attempt to obtain clarity – Implementer28CEO thinks he knows what is required but his definition is drastically at odds with what I was consistently told by ClientCompany28 management – this seems to evidence a level of arrogance or disinterest which is cause for concern

My understanding of the Essence of ClientCompany28’s business as seen by ClientCompany28 Executives and Management is “financial services – we want to be the leading provider of leasing solutions through the use of highly automated and highly advanced financial service software systems”

The goal of the project from ClientCompany28’s side is “Internet banking on steroids – fully interactive computer applications on the customers desk that allows them to tailor a vehicle lease, get a quote and authorize the quote and then allow ClientCompany28 to process that order through to delivery with minimum human intervention, includes allowing suppliers to pay themselves”

On a scale of 0 to 10 where 0 = we do not need computers and 10 = we are completely dependent on computers as in financial services and banking, ClientCompany28 management see their goal for this project as being to move them to a 9 or 10 and see themselves as already being at a fairly advanced level.  Implementer28CEO on the other hand sees ClientCompany28 as currently a 4 with the initial aim of the project being a 6 with possibly an 8 in due course but does NOT see this as a critical requirement

Implementer28CEO does not see 10 as necessary or achievable

Implementer28CEO’s description of the project and its goals is flowery sales speak and lacks precision and clarity

The biggest single reason this project is in difficulty is a lack of a clear, consistent and cogent statement of the goals of the project coupled with a substantial gap between Implementer28’s interpretation of the requirement and the actual requirement as stipulated consistently by ClientCompany28 Executives and Managers – it is my view that it is the responsibility of Implementer28 to make sure that they accurately understand the goals of their client

There are references to head-count reduction goals which, in my experience, are likely to be difficult to deliver on – head count reduction is the natural consequence of a well configured, well implemented ERP well operated and is a spin-off.  Making head-count reduction a goal introduces negative psychology and results in people trying to figure out how to reduce head-count rather than now to implement the system optimally

3.       Development project NOT an ERP project, AX is an inefficient development environment – 15%
As a direct outworking of the previous point, ClientCompany28’s requirement is for a highly tailored solution geared to delivering the highly intelligent customer interface and all supporting services necessary to create the competitive position outlined above

It appears that Implementer28 only fully realized that this was primarily a development project about six months ago and have since been resourcing accordingly

As far as I can determine Implementer28 are primarily a ERP configuration service provider and NOT a development house.  They have had to acquire development resources but still have to learn how to manage such resources (fundamentally different management to configuration) and the massive gap in strategic understanding referred to above will hinder this

It is important to understand that from a fundamental first principles consideration of ClientCompany28’s objective, as set out above, this was NEVER an ERP project, it has always been a development project

It appears that either Implementer28 totally failed to comprehend this in their initial presales negotiations or chose to ignore it and try to shoe-horn ClientCompany28 into AX no matter what the cost

Estimates of the level of custom development on this project run to as high as 75% but not lower than 30%.  There is NO question that this is a major custom development project and that Implementer28 grossly failed to recognize this and run the project accordingly

Further indications are that AX is a complex, cumbersome and highly inefficient development environment, one ClientCompany28 technical staff member referred to it as “horrible” – I do not have independent verification of this but repeatedly observed that it was very difficult to get clarity on what is being developed and that there is considerable jargon on the part of Implementer28 personnel

It should be noted that the development of an “Internet banking on steroids” solution for ClientCompany28 requires a front end customer interface that Is extremely lean, highly efficient (fast), robust, error free, etc – inherently this implies the use of high performance technology which as far as I can determine is NOT what AX offers.  There appear to be strong reasons to suggest that the customer interface should NOT be developed using the approach currently proposed

Coupled to this there is a fundamental issue in that the solution should be designed top down with the customer interface as the starting point – determine what is required in the customer interface and then build the rest of the customization to deliver this.  In this case there is no attempt to design and build in this manner

There appears to be a basis to circumscribe the extent of development undertaken in AX versus what might be undertaken using other technology

It appears that AxAddOn28 may only provide a 15% fit according to some interpretations and is therefore an inappropriate technology choice – at that level of fit it would be better to redesign from scratch.  Xxx appears to know of alternative technology which is allegedly a better fit

Changing from AX 2009 to 2012 mid-stream seems questionable given that there was so much custom development required – there is the paradox that many of the reasons why Informix has been rejected as a future platform are manifesting in the AX environment – e.g. massive upgrade effort – it is estimated that the move from 2009 to 2012 has delayed the project by 9 months, this is roughly the length of time it would have taken to port the current FourGen / Informix Xxx solution to the Xxx database platform which would allegedly have remediated the technical constraints on Xxx (note that Informix is owned by IBM)

4.       Implementer28 have failed to provide necessary professional guidance – 14%
From consideration of the previous points it will be apparent that I am of the opinion that Implementer28 have failed miserably to provide the required level of professional guidance and thought leadership with the result that a year to two years of time, hundreds of thousands of Pounds and tens of thousands of hours have been sub-optimally employed if not totally wasted

It seems that Implementer28 have spent three years without a robust clearly understood definition of the project goals – I would expect to see carefully designed posters setting out the project goals and main design elements, I asked close to ten people for the strategic concept document that allegedly exists but at the time of writing have not received a copy

Implementer28 have spent at least two years treating the project as an AX ERP configuration project when fundamentally it is a development project and AX is not necessarily then the most appropriate technology platform – by all means use AX as the ERP but that does NOT necessitate that high performance customer facing software has to be developed within the AX context and if AX is inhibiting development to the extent that some people seem to suggest then AX needs to be reconsidered

Implementer28 appear to have shifted considerable responsibility for the design of the solution to ClientCompany28 people with ClientCompany28 staff being taken out of production for very considerable periods of time to undertake documentation and workshops that appear to be outside their scope of knowledge and experience and producing mountains of theoretical documentation.  At this stage I have not been convincingly shown that these documents are resulting in a concrete and robust deliverable

It is my opinion that Implementer28 should have facilitated workshops with groups of ClientCompany28 people and that Implementer28 personnel should have produced the documentation in close cooperation with the development personnel in order to ensure robust specifications.  The basic process should entail:

- Walkthroughs of current way of doing things
- Outline by ClientCompany28 management of the future desired state
- Workshops with user populations, with Implementer28 analysts AND developers present
- Implementer28 analyst personnel produce documentation in consultation with business and developers
- Review draft specification in workshop setting with business users and developers
- Refine
- Review and refine again
- Adopt

It appears that the process that has ACTUALLY been followed is:
- Pull ClientCompany28 personnel out of the business
- Leave them to draft all sorts of documents they really do not understand
- Workshop in some way
- Present to management and get an explosion because management were not consulted at the start

As far as I can see Implementer28’s way of working is fundamentally flawed from a systems engineering perspective, it appears to be defective even from the perspective of limited tailoring of standard AX components in that it seems to be fundamentally a bottom-up approach

The ClientCompany28 team for the most part appear to be dedicated, loyal, passionate and trying really hard but from what I can see the defective Implementer28 approach has set them up for failure

It does not appear to occur to the Implementer28 consultants that if they are repeatedly doing weeks of work and being told by ClientCompany28 management that the results they are producing fail to meet business requirements that there is something wrong with the way Implementer28 are doing things rather than blaming ClientCompany28 – UNLESS ClientCompany28 have been consistently interfering with the work of the Implementer28 consultants and giving them direction and then not take responsibility for the outcome

It is firmly my opinion that a client engages the services of an external professional services firm like Implementer28 on the basis that they expect that firm to provide comprehensive guidance, thought leadership, strategic architectural guidance, etc – this appears to be consistently lacking in the services that Implementer28 have supplied

There are some VERY GOOD PEOPLE on the Implementer28 team but the high level leadership is lacking and there are rumbles that the top management of Implementer28 have refused to listen to the consultants on many occasions and made sales promises to ClientCompany28 that the consultants knew were false and that they could not deliver on

It does appear that Implementer28 are course correcting, Xxx and a number of his people appear to be highly competent and Xxx appears to be competent but they are operating within a defective governance framework from Implementer28 management and at this stage seem likely to produce more of the same unless the fundamental strategic definition issues outlined above are fully addressed

I have not been able to understand why moving to an “Agile” methodology is going to fix the problem when huge amounts of work have been done and it appears that the basic content of the work is defective

Certain Implementer28 consultants come across as very cocky and confident to the point of being arrogant without necessarily being able to demonstrate delivery

There is a massive deficit in terms of high level strategic guidance with regard to the design of the overall solution and, at this stage, while I think that the development team MAY be capable of delivering technically they need much clearer strategic direction and I am not sure that Implementer28 management have the knowledge and experience to run a project of this nature or else they are stubbornly refusing to acknowledge that there is something that they are doing which is fundamentally getting in the way of the core objectives of the project

There also appears to be a lack of Governance clarity on the Implementer28 team in terms of who is guiding the project overall

Fundamentally ClientCompany28 have very substantial and very valid reasons to deal very severely with Implementer28 – this having been said, the fact is that ClientCompany28 have made a huge investment in getting to know the AX environment and development platform and build relationships with the Implementer28 team and Implementer28 have made a commensurately huge investment in getting to understand ClientCompany28’s business and build relationships with ClientCompany28’s people – it is NOT in the interests of ClientCompany28 to terminate Implementer28 at this point BUT a major change in the way the relationship is managed is going to be vital

5.       ITManager28 is stretched excessively – 10%
It seems that ITManager28 is excessively stretched and that she has stepped up to the plate in various areas which have resulted in this situation

It is recommended that actions are taken to assist ITManager28 to focus on her core areas of real high value knowledge and experience relative to achieving the project outcome and provide resources to ensure that other activities are delegated to others – I understand that some recruitment measures are in place but would recommend that the exact specification of the human resources required be carefully evaluated in the light of this report before personnel are appointed or contracted

6.       ClientCompany28 need a very experienced and very senior project leader /  director – 12%
From ClientCompany28’s side it seems to me that the biggest gap if for a very senior, very experienced project leader / project director, not necessarily full time, to come in and take over the running of the project from the client perspective, someone who can engage in tough negotiations with the service provider, negotiate in terms of project scope on a peer level with executives, give strategic solution guidance, etc 

This is a role that I sometimes play, ClientCompany28CEO has asked me for a separate proposal in this context

7.       Outsourcing of the development of core strategic capability is not advisable – 2%
Given the very ambitious vision of ClientCompany28 and the core strategic capability that it is desired to develop I am not entirely comfortable with an external third party developing the elements of the software that are critically strategic, that is the software to sit on customers desks

I realize that it is late in the day to change the current contractual arrangements but I would suggest that the current arrangements are reviewed – it is vital that the core software development capability for core strategic value should be tightly held by ClientCompany28 and NOT be out in the market to be sold off to the highest bidder

Undertaking key elements of this development in-house should be carefully considered

8.       Fundamental database design and business intelligence design can start immediately – 8%
I strongly recommend a drastic rethink of the way the solution is being designed

The fundamental logical entities that make up the customer user interface and the  major building blocks of the solution, that is vehicles, accessories, customers, lease terms, etc, etc are well known and will not change – there is no reason a robust entity relationship map of fundamental data elements cannot be developed immediately

This document will then form the basis of:

-  Database design for the customer user interface
-  Design for the data warehouse and  Business Intelligence solution loading out of Xxx as an interim solution if required

The fundamental database design is a function of the business NOT AX, there needs to be linkage back into AX in some cases but if the view that up to 60% or more of the total solution will be custom developed then constraining this development because of the existence of AX must be questioned.

9.       Quality of validation data is average to poor requires critical attention – 6%
Quality of validation data is average to poor, the new Chart of Accounts seems fair but could be improved but other lists like the Accessory code require significant investment:



There is no logic in the above list on which software intelligence can be built

A well designed hierarchical list should replace this

Similar comments apply elsewhere

Note that a poorly configured ERP leads to all sorts of operational inefficiencies and increased operating costs – precision configuration is a critical requirement to achieving the goals set for this project and I have seen very little evidence of precision configuration – thus, while this point has a relatively low weight it is nevertheless critical once the other issues have been addressed

10.   Remediating and strengthening Xxx should be investigated further – 4%
The possibility of falling back to Xxx was explored

There ARE apparently interface issues with the Informix Database that are inhibitors to change but further research in this field may be warranted

Conversion to the Xxx database would open up the database but is estimated to take two senior developers twelve months and does carry risks.  Once this was done ClientCompany28 would be able to use a diversity of development technology to enhance the Xxx solution long term

Note that it would be necessary to pay premium salaries for key developers but it is likely that these salaries will NOT be any more than are required for AX developers

There does appear to be a basis to conclude that the decision to trash Xxx was not necessarily the best decision given the real strategic priorities, it is almost certain that if ClientCompany28 had remained with Xxx, converted the database and run a tight project in lines with past experience that a new customer interface would have been deployed and fully operational at least a year ago

The above findings point to a number of areas of uncertainty that require further investigation in order to arrive at a robust way forward.  Proposed actions are discussed in the next section of this report

Overall it appears that the project can be stabilized and managed to achieve a successful outcome but some significant changes in approach are called for

Recommended Actions
Following are the recommended actions following on tabling of this report:
1.       Appoint executive level project leader /  director – 28%
ClientCompany28 need an executive level individual, probably part time, to drive this project for them – need considerable systems, project management / leadership experience, architectural ability, etc – this person should lead and guide the execution of all the points below

2.       High level solution design and documentation – 23%
Run a series of workshops at the Executive level to arrive at a robust and comprehensive high level specification of the required business outcome (Internet on steroids) and produce comprehensive documentation down to the level of the individual user interface screens that the customer will interact with

3.       Evaluate sustainability of Xxx – 14%
Undertake further research to establish whether there are alternative solutions to the problems with Informix interfacing in order to make Xxx more viable as a fall-back position

Note that Informix is now owned by IBM so I would expect there to be fairly robust alternative solutions to the problems that were described to me in terms of interfacing

4.       High level walkthrough and more in-depth evaluation of state of AX project – 11%
I had great difficulty getting a real hands-on feel for what is there, some people said almost nothing and others say a considerable amount

The only way to answer this is to get all the key people in a room for a day or two days and have the Implementer28 and ClientCompany28 teams walk us systematically through what has been done in terms of practical demonstration of documents, screens, etc

At the end of this process take a final decision as to whether there really is a case to continue with AX or fall back to Xxx and alternative technology is warranted

5.       More detailed evaluation of Implementer28’s performance – 9%
For the reasons indicated above it is difficult to gauge Implementer28’s performance – as far as I can see I would give them about 2/10 but a few people seemed to point to better performance

The proposed walkthrough above will give a better indication of whether Implementer28 is just offering good sales talk and technical sub-standard work or is able to deliver – note that I think that provided the way in which they are managed is significantly changed there is a reasonable basis to expect that they can deliver provided we prevent loss of further key personnel

I do NOT think that Implementer28 should be terminated unless it is found that there really is nothing of substance to show for the work done so far but I DO think they need to be managed very differently

6.       Project to deliver customer solution as rapidly as possible – 7%
I am reasonably certain that with limited technical adjustments and compromises it should be possible to start designing and developing the software to sit on client desk-tops in the near future, to run against Xxx if necessary initially

7.       Precision configuration (taxonomy) activities – 5%
Precision code tables should be developed – refer my Taxonomy Manual for reference

8.       First principles data warehouse and business intelligence design – 3%
As with the customer interface, the design of the master tables for the Data warehouse should commence soon and not be further delayed and the same with the Business Intelligence design

Conclusion

There appear to be major reasons for dissatisfaction with Implementer28 and reasons for concern with the current project status

 

Measures should be taken that improve team morale, improve focus and build on what it good in the project environment which appears to be significant and improving – we should NOT break what is in the process of getting fixed

Having said this there is a need for appointment of a senior advisory / leader to ClientCompany28 to direct the project, proper definition of high level project goals, more in-depth assessment of the value of the work done to-date and other actions directed at ensuring a high value outcome

 

I am available to assist in whatever way ClientCompany28 require to give effect to these recommendations.



Dr James A Robertson PrEng

The Essence of the Pulse Measurement

A concise high impact investigation that quickly delivers an accurate diagnosis of the cause of system problems in Business Language that makes sense to executives coupled to prescription of practical and actionable treatment

IF you have the SLIGHTEST RESERVATIONS about whether you are obtaining the full value from your Business Systems and ERP investments;

or are in the least bit concerned that your systems are HARMING YOUR ORGANIZATION;

or your project is stalled;

or you want a view on the best way forward;

or you want to embark on procurement of new systems and need high level guidance;

or simply want an independent second opinion on any business systems related matter;

then contact us NOW

The fees are MINIMAL relative to the savings that many clients have experienced

And IF you are NOT fully satisfied with the service after the first day you may terminate the engagement and pay ONLY travel and expenses outside of London

 

For more information visit the main Pulse Measurement page


Click here to email us now to discuss your requirements and obtain a proposal without obligation


Random Selection of Articles by Dr James Robertson

Dr James A Robertson PrEng

Business Systems NOT delivering?

Call the Business Systems Specialist

Dr. James Robinson

Dr James A Robertson -- has been involved in the effective application of Business Information Systems, including but NOT limited to ERP, since 1987 and in the profitable and effective use of computers in Business since 1981.

Drawing on a diversity of experience, including formal military training in Quick Attack techniques at the Regimental Commander level, Dr Robertson has developed highly effective methods of investigating any sub-optimal Business Information Systems situation -- be it an established system or a stalled project or any other source of Executive frustration -- quickly and concisely diagnosing the root cause of the problem and prescribing concise practical actions that Business Executives can effectively act on see the Pulse Measurement page and also the Sample Reports page for redacted real reports.

He has also developed highly effective methods of strategically enriching systems to unlock the full potential of existing investments, see the Precision Configuration page and couples this to architecting small pieces of clever software that harness the full potential of your investment, see the Software page.

If you are having problems with your systems, your project or your IT Department, call The Business Systems Specialist
James@James-A-Robertson-and-Associates.com

Business System Failure is RIFE -- we offer insight into why this happens AND WHAT is required to prevent it.

Failure is at epidemic levels with massive damage done to client companies -- if you are NOT aware of the extent of the problem please visit the About Failure page for a catalog of major failures running to billions of Pounds and Dollars.

All evidence indicates that the established players do NOT know how to deliver stable, reliable high value solutions that WORK.

There HAS to be a better way!

This website provides information relating to that way with a large collection of white papers, presentations, standards documents, etc that you can use to start bringing the situation under control

We also offer high level advisory services with regard to the application of the principles advocated on this website

We offer an ENGINEERING APPROACH to addressing these issues

Click here to read more about the Engineering Approach

By Engineering I mean the formal, structured, highly disciplined, highly systematic, highly practical approach that consistently delivers results in ALL areas of human endeavor where formally trained and certified engineers are the ONLY practitioners permitted to operate -- think large buildings, factories, motor vehicles, aircraft -- highly complex systems that work at a level that we take it for granted that they WILL work and where failure is all but unthinkable and, when it happens, attracts immediate public attention and rigorous investigation directed at ensuring that such failures are prevented in the future -- in fact, everything that the management consulting industry that implements complex software systems is NOT

This approach is discussed further on the Engineering Approach page.

Search Articles


Random Selection of Articles by Dr James Robertson

Std 027 COBOL – old software CAN be retained (with reference to Bridgestone)

Many organizations replace COBOL systems because they have been told they are obsolete, this article dispels that myth
Std 011 Procurement: 03 Business Information System Requirements Definition

The Business Requirements Specification is a strategically focused document, that is it lifts out the essence of the business and how it thrives in a structured and weighted manner so that there is NO uncertainty on the part of the bidders as to the exact nature of the business
The strategic essence must lift out the fundamentals of the busines and particularly what is unusual, the elements that deliver competitive advantage and which are therefore the most vulnerable to inappropriate action
This is NOT the place for generic industry definitions or for long lists of standard software functionality -- development of the requirements specification requires a mature and highly experienced consultant with a solid understanding of strategic essence AND a solid understanding of systems and how systems integrate with the business to deliver high value outcomes
Std 028 Why Regular Communication between the Project Leader and the CEO is Vital

A business information systems project that extends across the full ambit of the organization is almost certainly the most difficult and most challenging project that any organization can undertake.  This MUST be driven by the CEO as custodian and supported by a highly experienced and very mature Project Leader.  These two people must communicate constantly and effectively in order to ensure that they remain aligned to give the CEO the solution that is required

Book -- The Critical Factors for Information Technology Investment Success

In 2003 I undertook an in-depth analysis of all the information and experience that I had gathered with regard to the factors giving rise to Business Information System failure including ERP and general IT and classified this information into a number of categories including "The Factors Causing Failure" and "The Critical Factors for Success" based on this I developed a two day Course "The Critical Factors for Information Technology Investment Success" which is still offered today.

Based on this I wrote the book of the same name, which is available in electronic form here for download:

Subscribe to our Newsletter

Click here to send us an email subscribing to our free newsletter -- all articles posted by James Robertson will be emailed to you

Detailed information about James Robertson on LinkedIn

James has a very detailed profile on LinkedIn should you require further information about him.

You can also connect with him on LinkedIn at http://www.linkedin.com/in/DrJamesARobertsonERPDoctor

James has an open networking profile -- click on "Connect" and use email address James@LinkedIn-at-JARA.com.

Contact Us

You can contact us on

Email: James@James-A-Robertson-and-Associates.com

LinkedIn at http://www.linkedin.com/in/drjamesarobertsonerpdoctor

Facebook at https://www.facebook.com/james.a.robertson.393

Mobile: +44 (0) 776-862-2875

Landline: +44 (0) 207-059-0007

Fax: +44 (0) 844 774 4580

Articles by James A Robertson and Associates

There is a large body of white papers, articles and other content produced by Dr James Robertson available on this website

Please click here to visit the detailed listing of articles



ArticleTagCloud for Articles Published by James A Robertson and Associates

7 steps to FIX your ERP      80:20 regarding software replacement      aborted projects      abstract      abstractness      accounting      actionable      adjudication      Advantage Data Transformer      advisory      agreement      all possible classifications      all reports      all software elements required      all spreadsheets      all tasks required to execute the project      Alpha Omega      analysis of data      analytics      animation      answers to the questions we have NOT yet thought to ask      Armscor      arrogant ignorance      art of strategic business information system project leadership      ASCO      attendance register      attorney      audit      audit cost reduction      bankrupt organizations      basis for achieving alignment      basis of payment      basis of pricing      better way      bid adjudication      bid adjudication score sheet      bid compliance      bid compliance checklist      bill of materials      bill of services      BIS      BIS failure      BIS success      boots in the mud      BPM      BPM dangerous      BPM distracting      BPM ineffective      brainstorming      break it until it does NOT break anymore      break it until it will NOT break any more      budget      budgeting      business engagement      business executives      business improvement      business information system      business information system failure      business information system success      business information system taxonomies      business information systems      business information systems procurement      business information systems projects      business integration      business intelligence      business intelligence models      business knowledge and experience      business participation      business process      business process mapping      business requirements focused      business requirements specification      business simulation laboratory      business systems      business systems laboratory      business understanding      by the book      care      case studies      case study      CEO      CEO -- project leader communication      CEO as custodian      CEO definite views      certificates      challenges      challenging presentations      change facilitation      change for strategic reasons      chart of accounts      classification schemes      clever software      client changing scope      client compact      clinical codes      coaching      Cobol      COBOL CAN be retained      Cobol still viable      code schemes      coding conventions and standards      cognitive span      collapse      communication      competitive advantage      competitive advantage through precision configuration      competitiveness      compiler      complexity      compliance      compliance checklist      comprehensive testing      Compuware      conference speaking      conferences      confidentiality      configuration      consultant NOT delivering what required      contract      contract certificates      contract law      contracting      contractors      corporate planning      cost      cost-quality-time      CPT 4      CPT4      critical factors      critical factors for IT investment success      critical factors for success      critical factors for technology success      critical human foundation      critical issues      critical issues analysis      critical requirements      CRM Risk Control      cubic business model      custom development      custom software      customer focused      data      data content      data engineering      data entities      data warehouse      DB2      definitions      design against failure      design and development      design for success      determination of strategic essence      determining strategy      diagnostic code      diamonds in the dust      differentiated      differentiation      diffusion of innovations      discovery      dislike of failure      dispute resolution      do NOT change systems because of alleged software redundancy      do things competitors could NOT do      document pack      Dr James A Robertson      Dr James A Robertson PrEng      dramatic benefits      dramatically improved strategic management information      driver of success      Dunning-Kruger effect      ease of use      economic collapse      economics      effective communication      effectiveness      efficiencies      efficiency      efficient filing of emails      eliminate light bidders      email      engineer against failure      engineered data      engineering      engineering approach      engineering approach to strategy      engineering failure      engineering laboratory      engineering services      engineering solution design      engineering techniques      enhance differentiators      enhance the differentiators      enhancing the value of your present investment      ensuring project success      enterprise resource planning      ERP      ERP configuration      ERP failure      ERP procurement      ERP success      ERP taxonomies      ERP value      essence IS different      essence of business      essence of the business and how it thrives      ethics      examples      exceptionally bad code design      executive briefing      executive briefings      executive custody      executive decision support      executive engagement      executive forum      executive frustration      expose hidden agendas      facilitation      factors causing failure      factors causing IT investment failure      factors causing technology failure      factors to manage for success      failure      failure to address soft issues      fashion      file table of contents      Financial Information System      financial information systems      financial management      fixing your ERP      focus for projects      folder design      foundation for delivery      full training      functional entities      future      Gantt Chart      gap analysis      general ledger      George Paton      go-live      go-live certificate      governance      governance = care      governance failure      group consolidation      Group Consolidation Chart of Accounts      growth      gut feel factors      hand holding      harshest judge of governance      hate failure      head count reduction      health management software      hierarchies      high level requirements      high road      high value      high value implementations      high value solutions      high value systems implementation      highly effective chart of accounts      holistic view of solution      how do you achieve executive custody      how the organization differentiates itself      how to      how to do it      huge opportunity      human foundation      hype      Hyperion      IBIS      ICD 10      ICD10      importance of executive custody      improved management information      in-box rules      incremental enhancement of existing systems      ineffectiveness      inefficiency      information required from third party suppliers      information technology      information technology failure      Information Technology Strategy      information technology success      Informix      in-house courses      innovative software solutions      innovator      inside head of CEO      insightful      instructions      intangible      integrated business information system      integrated view of business      integrity      intelligent data      interactive training material      interview      invitation to bid      isolated CEO = explosion      IT      IT and strategy      IT Audit      IT failure      IT governance      IT lies      IT management      IT mythology      IT non-performance      IT people who lie      IT personnel socialization      IT procurement      IT projects that fail      IT strategy      IT systems      IT systems procurement      IT the harshest judge of governance      James Robertson      Jof Nelson      key performance indicators      Kirsten Speer      knowledge management      laboratory      lack of an engineering approach      lack of precision configuration      lack of strategic alignment      lawyer      leadership      legal agreement      legislation      lies      list of required software      listen carefully      litigation      logical entities      loss information      low road      loyalty      MacDonald      maintain code schemes      maintenance      maintenance management      Malcolm McDonald      management      management information      managing contractors      manual      marketing hype      master data      master data classifications      master test data      mature facilitation      mature facilitator      measurable      measures of alignment      mentoring      Microsoft Outlook      misrepresentation      missing link      mistique      morals      Munich      mystique      mythology      new future state      New South Africa      no drill down      non-disclosure      NOT classic project management      obsolete is a fashion statement      obsolete software      old software IS viable      once software works it always works      on-line seminars      opportunities      opportunity to turn the economy around      organizing Microsoft Outlook      orientation of IT staff      own business experience      passion to enable clients to thrive      people are part of the system      personality matrix      planning      platform for a tough contract      precisio      precision      precision configuration      precision configuration advisory      precision configuration leadership      precision data      precision taxonomies      Predictive Index      preparatory steps      prescribed table of contents      presentation technique      presentations      preventing failure      preventing falure      preventing project failure      pricing      principles      problem statement      procedure code      process      processor ignorant of language      procurement      procurement timeline      professional speaker      Professional Speakers Association of Southern Africa      profitability      programming languages are for the programmer      project facilitation      project leader      project leader -- CEO communication      project leadership      project management      project management IT project management      projects      prove it works      PSASA      psychology      psychometrics      public conferences      public presentations      public speaking      Pulse Measurement      quality      REAL issues in Business Information Systems      REAL value      recognizing failure      redaction      reduced audit costs      reduced head count      reference documents      Reg Barry      regulatory body      relationship Almighty      relationship orientated      remediation of existing systems      Rennies Group      reports      reports not reliable      request for proposal      requirements specification      results orientated      RFP      right things      rigorous process      rigorous strategic planning      risk management      Robert Priebatsch      robust business information systems procurement      robust business systems procurement      robust contracts      robust procurement      robust solutions      SAICE      SAP ABAP is similar to COBOL      scheduling procurement      scientific professional      score sheet      screen design      seminars      SEPT      service orientated      Service Orientated Architecture      simple techniques to enhance business information systems value      simulation      sloppy configuration      SOA      socialization      software      software assets      software design      software does NOT wear out      software is instructions for the bricklayer      software schedule      software specification      software specification standards      solution experience      solution knowledge      South Africa      South African Institution of Civil Engineering      speaking      Spirit Led      standards      strategic      strategic advisory      strategic alignment      strategic analysis      strategic analysis and design      strategic business improvement      strategic custom development      strategic definition      strategic discovery      strategic driver      strategic driving force      strategic engineered precision configuration      strategic engineered precision taxonomies      strategic essence      strategic financial information      strategic gap analysis      strategic governance      strategic information      strategic management      strategic management information      strategic plan      strategic planning      strategic project leader      strategic snapshots      strategic software      strategic solution architect advisory      strategic solution architect leadership      strategic solution architecture      strategically designed chart of accounts      strategy      strategy defined      strategy focused planning      Strategy Snapshot Toolset      StratGap      StratSnap      strengthen differentiators      structured analysis      structured chart of accounts      substantial management information      succeed by engineering against failure      success      successful deployment      survive      system knowledge and experience      table of contents      tailored presentations      take notes      taxonomies      taxonomy      taxonomy software      technology      technology failure      technology issues      technology management      tender document pack      tender pack      tender pack table of contents      test data      testing      The Critical Factors for Information Technology Investment Success      the Critical Factors for Success      the essence of the business      the essence of the business and how it thrives      the essence of the organization and how it thrives      the factors causing failure      the first hour      The REAL Issues in Business Information System success      things right      third party suppliers      third world countries      thrive      time      tipping point      tough certificates      tough contract management      tough contracts      tough procurement      tough terms      training      training material      treatment code      understanding of data      understanding the engineering approach      Uniface      unlocking value      use different languages for new components      V3 Consulting Engineers      validation data      value      versus process      video      webinar      webinars      weighted factors      what is executive custody      what is strategy      what is the essence of this organization and how does it thrive      what to do      where is IT going      why executive custody is required      why the organization exists and how it thrives      why your business information system is NOT delivering and HOW to FIX it      why your ERP is NOT delivering and how to fix it      workflow      writer     

Table of Contents

Home

About Dr James A Robertson PrEng -- The Business Systems Doctor -- and Other Topics

Catalogue of Major Business Information System Failures

About the Engineering Approach

James Robertson's Value Add

Attributes of a HIGH VALUE solution

Recognizing Business System Failure

The Critical Human Foundation

Old Software IS Viable

From South Africa

Competencies of Dr James A Robertson PrEng

About Professor Malcolm McDonald

Table of Contents

About my relationship with the Almighty Creator, Yah the Eternally Self-Existing

Comments relating to the Business Systems Industry and other topics

Testimonials and other positive material regarding James Robertson

Reference Articles

List of Articles

Article Catalogue

Achieving High Value Business Information System outcomes

Executive Custody -- What is it and HOW do you get it?

The REAL Issues in Integrated Business Information System Success

Part 1: Introduction

Part 2 -- Mythology and Lack of Executive Custody

Part 3 – Strategic Alignment and Precision Configuration

Why your ERP is NOT delivering and HOW to FIX it

IT Project Management

Pulse Measurement

CEO Anthony Lee Comments on his experience of the Pulse Measurement

No Charge Guarantee on the Pulse Measurement Service

Examples of Pulse Measurement Outcomes

Critical questions regarding the Pulse Measurement™

The Pulse Measurement Workflow

The Critical Factors for Business System (ERP+) Investment Success in the Pulse Measurement

Indicative Pulse Measurement Durations

What is a JAR&A Pulse Measurement?

Survival of the fittest – why it makes sense to measure the pulse of your business

Examples of Pulse Measurement Outcomes over 24 years

Sample Pulse Measurement Reports

Strategy

Strategic Essence: The Missing Link in Business Information Systems

Strategic Essence: Overview

Strategic Essence: Part 1 -- Strategy Defined

Strategic Essence: Part 2 -- Differentiation

Strategic Essence: Part 3 -- The Essence IS Different

Strategic Essence: Part 4 -- The Essence should be the Point of Departure

Strategic Essence: Part 5 -- Discovering Strategic Essence

Strategy -- the Essence of the Business: What is it and how do you develop actionable strategic plans?

Simple Steps to Increase the Strategic Value of your ERP Investment

Free Strategic Snapshot Toolset and Manual

A strategy focused planning system beyond traditional budgeting

Tough IT and ERP Procurement and Contracting that Works

Robust Business Systems Procurement

Part 1 -- Introduction

Part 2 -- Bill of Services, Laboratory, Go-live Certificate, etc

Part 3 -- Executive Engagement, Bid Compliance, Adjudication and other matters

Procurement Documents

Guidance and Advisory Services

The Art of Project Leadership

Why Regular Communication with the CEO is Vital

The Business Simulation Laboratory

Precision Configuration and Strategic Business Information Architecture

Precision Configuration based on Strategic Engineered Precision Taxonomies

The JAR&A Cubic Business Model

Highly Structured Strategic Chart of Accounts -- a Vital Element of your Corporate Information Arsenal

The Product Catalogue -- an Essential Element of any Precision Configuration

Attributes -- answers to the questions you have NOT yet thought to ask

Case Studies of Notably Successful Projects with high value Precision Configuration

092 Doing things differently and better -- ASCO Case Study 2-- BPM Summit 2013

088 Strategic ERP Invesment -- ASCO Case Study -- Service Management Conference and Exhibition Africa

026 Information Architecture and Design of FIS for Rennies Group -- Financial Information Systems Conf

018 CRM Risk Control: Designing and Implementing an Integrated Risk Mgmt Sys -- Integrated Risk Mgmt Conf

011 V3 Consulting Eng: Benefits of MIS to Professional Practice -- SAICE 15th Ann Conf on Computers in Civil Eng

Strategically Enriching your Business Information Systems

Part 1 -- Introduction

Part 2 -- Principles of Data Engineering

Part 3 -- Steps in applying these recommendations

Simple Steps to increase the strategic information value yield from your Business Systems Investment

The Full JAR&A Taxonomy Manual

Part 1: Introduction, Problem Statement, Definitions and Examples

Part 2: Why Use JAR&A, Required Knowledge and Experience, Cubic Business Model and Chart of Accounts and Taxonomy Software

Part 3: How to do it, Case Studies and White Papers and other References

Example General Ledger Manual

Business Process -- Irrelevant, Distracting and Dangerous

The RIGHT Approach

Custom Strategic Software Design and Oversight of Construction

Standards for Custom Software Specification

What IS Software?

IT Effectiveness

Organizing Outlook

Critical Factors for I.T. Success

A Moral and Ethical Dilemma -- Systems that Fail

Case Studies examining Business Information System failures

The BBC Digital Media Initiative Debacle

The Bridgestone -- IBM Conflict

Speaking and Training

Showcase of Conference Presentations

Most Viewed Presentations

Briefings and Seminars

Why your ERP/BIS is NOT delivering and HOW to FIX it

ERP and IT Procurement that Delivers Results

The Critical Factors for IT and ERP Investment Success

Other Seminars

Conferences and Public Presentations

Conferences 80 to 99 -- 2009 to Present

Conferences 60 to 79 -- 2005 to 2009

Conferences 40 to 59 -- 1996 to 2005

Conferences 20 to 39 -- 1994 to 1996

Conferences 01 to 19 -- 1989 to 1994

On-Line Seminars (Webinars)

Webinar on Preparing and Presenting Webinars

Contacting James A Robertson and Associates Limited